top of page

South Crest 10Ml Reservoir

Project Status: Completed

Project Duration: 16 Months

Project Cost: R30M

ABOUT THIS PROJECT

In 2017, following a Feasibility Study by external service providers, the City of Ekurhuleni commenced with their bulk water infrastructure renewal programme.

​

Following a lengthy procurement process by CoE for professional service providers, AFI Consult was awarded the work as preferred service provider for the construction of the Alberton South Crest 10Mâ„“ Reservoir and work commenced in all earnest. 

DJI_0384.JPG

Following the detail design process, the scope of work included the construction of a 10Mâ„“ concrete reinforced post-tensioned reservoir with subsidiary works such as earthworks, interlinking pipework, the hydraulic control room, mechanical and electrical works.

​

The project was completed and successfully handed over to the employer during March 2021 for the total amount of R30M.

 

20191111_111652.jpg
20190812_135956.jpg
20191115_090340.jpg

Acknowledgement

We are pleased to acknowledge contributions made by the professional team in delivering the project successfully and save to the expectations of the City of Ekurhuleni and the community of Alberton nl;

  • R Torry (Pr. CPM)

  • K Chihota

  • JN Botha (PrEng.)

: Icon Construction - Project Manager

: City of Ekurhuleni

: AFI Consult - Project Manager

​

 

​

IMG-20200225-WA0001.jpg
DJI_0023.JPG
20200908_155137.jpg
IMG_20200917_DJI (3).JPG
IMG-20201208-WA0008.jpg
IMG_20210114_102852.jpg
bottom of page