Isando 15 Ml
Reservoir

Project Status: In construction

Project Duration: 12 Months

Project Cost: R60M

About this project

In 2017, following a Feasibility Study by external service providers, the City of Ekurhuleni commenced with their bulk water infrastructure renewal programme.

Following a lengthy procurement process by CoE for professional service providers, AFI Consult was awarded the work as preferred service provider for the construction of the Isando 15Mℓ Reservoir and work commenced in all earnest. 

DJI_0445.JPG

Following the detail design process, the scope of work included the construction of a 15Mℓ concrete reinforced post-tensioned reservoir with subsidiary works such as foundation piling earthworks, interlinking pipework, the hydraulic control chamber, mechanical and electrical works.

The reservoir is currently in construction with the completion date scheduled for September 2021 for the total amount of R60M.

 

 

Isando (1).jpg
Isando (5).jpg

Acknowledgement

We are pleased to acknowledge contributions made by the professional team in delivering the project successfully and save to the expectations of the City of Ekurhuleni and the community of Isando nl;

  • T Molefe

  • K Chihota

  • E Jooste

: Isipethu Water Services - Project Manager

: City of Ekurhuleni

: AFI Consult - Project Manager

 