Johannesburg Water Reservoir Renewals

Project Status: Design Development

Project Duration: 13 Months

Project Cost: R200M

ABOUT THIS PROJECT

In 2023, Johannesburg Water commenced with their reservoir renewal programme.

​

Following a lengthy procurement process by Johannesburg Water for professional service providers, AFI Consult was awarded the work as preferred service provider for the renewal of Aeroton, Hursthill No.2, Marlboro and Alexander Park and work commenced in all earnest. 

IMG20240202142535.jpg

Following the detail design process, the scope of work included the construction of a 15Mâ„“ concrete reinforced post-tensioned reservoir with subsidiary works such as foundation piling earthworks, interlinking pipework, the hydraulic control chamber, mechanical and electrical works.

​

Towards the end of 2021, following huge delays relating to the World Wide COVID-19 pandemic and MFA policy guidelines, the CoE opted to appoint an alternative service providers. The Contract Administration and Inspection Stage is underway under their auspices with completion expected towards the end of 2022. We remain proud of our contribution towards the Isando 15Ml Reservoir.

Isando (1).jpg
Isando (5).jpg

Acknowledgement

We are pleased to acknowledge contributions made by the professional team in delivering the project successfully and save to the expectations of the City of Johannesburg and Johannesburg Water nl;

  • S Tshuma

  • M Maluleke

  • K Coomans

: Johannesburg Water - Project Manager

: Johannesburg Water - Project Manager

: AFI Consult - Project Manager